Halloween Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

During a complex, multiyear project, a PM must discern which project tasks overlap so resources can be allocated appropriately. Which of the following is best for determining this information?

A.

PERT chart

B.

Milestone chart

C.

Gantt chart

D.

Budget burndown chart

A project manager working in a strong matrix organization was selected to manage a new project with trending technologies. During the kickoff meeting, one of the stakeholders mentions that the company has never worked with such technologies. Which of the following should the project manager do next?

A.

Train the project team members and develop a detailed scope statement.

B.

Assign project resources and procure additional team members.

C.

Perform a preliminary procurement needs assessment and determine budget considerations.

D.

Define units of work and develop a project schedule.

A global shipping slowdown is causing critical raw materials needed for manufacturing to be delivered late. As a result, a project's production run will be delayed from the beginning.

Which of the following dependencies is most likely happening?

A.

Finish-to-start

B.

Start-to-start

C.

Finish-to-finish

D.

Start-to-finish

Which of the following is a potential challenge that may arise from language barriers among a project team?

A.

A project team is unable to communicate effectively due to a lack of common technical terminology and jargon.

B.

A project team refuses to learn foreign languages to cater to remote colleagues.

C.

A project team cannot use communication tools due to a lack of IT knowledge.

D.

A project team member located in a different time zone fails to access project resources.

During the testing phase of a project, the legal department rejected a deliverable due to compliance issues. The project manager reviewed the risk register and triggered the mitigation plan for this item. Which of the following documents should the project manager update next?

A.

Schedule

B.

Status report

C.

Issue log

D.

Task board

Which of the following PRINCE2 processes includes creating the project plan?

A.

Starting up a project

B.

Initiating a project

C.

Managing product delivery

D.

Directing a project

A project manager has been assigned to a new project. During the planning phase, the project manager needs to get an understanding of the purpose of the project. Which of the following should the project manager do?

A.

Collate the lessons learned.

B.

Perform a gap analysis.

C.

Review existing artifacts.

D.

Conduct a retrospective.

A project manager must determine how ideas from the organization and results from the review committee should move through the enterprise for a new project. Which of the following does the project manager need to do?

A.

Establish communication channels

B.

Plan a kickoff meeting

C.

Develop a responsibility assignment matrix

D.

Identify the stakeholders

A project team is working remotely from different locations across the country. As part of a lessons-learned exercise, the project manager would like to

identify the level of engagement among project team members. Which of the following would be the best tool for the project manager to use?

A.

Meeting chat

B.

Email

C.

Real-time survey

D.

Whiteboard

During the testing phase of a project, the regression test fails due to a specific item that is disrupting the entire system. Which of the following documents should the project manager use to identify who requested this item?

A.

Issue log

B.

Risk register

C.

Defect log

D.

Traceability matrix