A company that is implementing an updated version of its main product hired a new project manager to lead the project. Prior to the start of the project, the sponsor asked the project manager to prepare a report on the defects found in the previous project to avoid a decrease in production. The report shows that the two main defects are related to cosmetic and physical damage to the product. Which of the following charts would BEST prioritize which defects to address?
During an executive call, a project sponsor found out about issues with the project but was not able to provide details about the next steps. Which of the following needs to be revised?
A project manager is currently meeting with a vendor who completed the project work. All invoices associated with the project have been paid. Which of the following best describes the project manager's objective for the vendor meeting?
A project is running over budget, and due to new legislation in the country, the company needs to release all its contractors on the project or hire them as full-time employees. Which of the following should the PM do next to comply with the new legislation?
A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?
A team member needs to make an emergency update. The team member is unable to return to the office. Which of the following is the most secure way to make the update?
A project manager and team are reviewing a task that is supposed to take 9 days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional 5 days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?
During the planning phase, a team agreed on the tasks, durations, predecessors, and resources needed to complete a project. Which of the following should be developed to formalize this agreement?
Which of the following activities are important parts of the closing phase? (Select two).
Which of the following is a quality assurance tool?