Weekend Sale - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

Your Appian project just went live with the following environment setup; DEV > TEST (SIT/DAT) > PROD

Your client is considering adding a support team to manage production defects and minor enhancements, white the original development team focuses on Phase 2 Your client is asking you for a new environment strategy that will have the least impact on Phase 2 development work.

Which option involves the lowest additional server cost and the least code retrofit effort?

A.

Phase 2 development work steam: DEV > TEST (SIT) > STAGE (UAT) > PROO

Production support work stream DEV > TEST2 (SIT/UAT)>PROO

B.

Phase 2 development work Stream: DEV > TEST (SIT) > STAGE (UAT) > PROO

Production support work stream DEV2 > STAGE (S1T/UAT) > PROD

C.

Phase 2 development work stream: DEV > TEST (SIT/UAT) >PROD

Production support work stream DEV > TEST2 (SIT/UAT) > PROO

D.

Phase 2 development work stream: OEV > TEST (Srr/DAT) > PROO

Production support work stream. DEV2 > TEST (SIT/UAT) > PROD

You are selling up a new cloud environment. The customer already has a system of record for Its employees and doesn't want to re-create them in Appian. so you are going to Implement LDAP authentication.

What are the next steps to configure LDAP authentication?

To answer, move the appropriate steps from the Option list to the Answer List area, and arrange them in the correct order. You may or may not use all the steps.

Your Agile Scrum project requires you to manage two teams, with three developers per team. Both teams are to work on the same application In parallel.

How should the work be divided between the teams, avoiding issues caused by cross-dependency?

A.

Group epics and stones by technical difficulty, and allocate one team the more challenging stories

B.

Group epics and stones by feature, and allocate work between each team by feature.

C.

Allocate stories to each team based on the cumulative years of experience of the team members.

D.

Have each team choose the stones they would like to work on based on personal preference

What are two advantages of having High Availability (HA) for Applan Cloud applications?

A.

An Applan Cloud HA instance is composed of multiple active nodes running in different availability zones in differentregions.

B.

Data andtransactions are continuouslyreplicated across the active nodes to achieve redundancy and avoid single points offailure.

C.

A typical Appian Cloud HA instance is composed of two active nodes.

D.

In the event of a system failure, your Appian instance will fie restored and available to your users in less than 15 minutes.having lost no more than the last 1minute worth of data.

You are deciding the appropriate process model data management strategy.

For each requirement. match the appropriate strategies to implement. Each strategy will be used once.

Note: To change your responses, you may deselect your response by clicking the blank space at the top of the selection list.

For each scenario outlined, match the best tool to use to meet expectations. Each tool will be used once

Note: To change your responses, you may deselected your response by clicking the blank space at the top of the selection list.

You have an active development team (Team A) building enhancements for an application (App X'). and ate currently using the TEST environment for UAT.

A separate operations team ('Team B) discovers a critical error in the Production instance of App X that they must remediate However. Team 6 does not have a hotfix stream for which to accomplish this The available environments are DEV. TEST, and PROD

Which risk mitigation effort should both teams employ to ensure Team AS capital project is only minorly interrupted, and Team B s critical fix can be completed and deployed quickly to end users?

A.

Team 8 must communicate to Team A which component will be addressed in the hotfix to avoid overlap of changes It overlap exists, the component must be versioned to its PROD state before being remediated and deployed, and then versioned back to its latest development state If overlap does not exist, the component may be remediated and deployed without any version changes

B.

Team A must analyze their current codebase in OEV lo merge the hotfix changes into their latest enhancements. Team B is then requited to wait for the hotfix to follow regular deployment protocols from DEV to the PROO environment.

C.

Team 8 must address changes in the TEST environment These changes can then be tested and deployed directly to PROD. Once the deployment is complete. Team B can then communicate their changes to Teams to ensure they are Incorporated as a part of the next release.

D.

Team 8 must address the changes directly in PROD. As there is no hotfix stream, and OEV and TEST are being utilized for active development it is best to avoid a conflict of components. Once Team A has completed their enhancements work. Team 6 can update DEV and TEST accordingly.

You are required to create an integration from your Appian cloud instance to an application hosted within a customers self-managed environment.

The customers IT team has provided you with a REST API endpoint to test with; httpsV/lnternal networkVapi/api /ping

Which recommendation should you make to progress this integration?

A.

Expose the API as a SOAP-basedweb service.

B.

Deploy the API / service into Appian Cloud

C.

Add Appian Cloud's IP address ranges lo the customer network's allowed IP listing

D.

Set up a VPN tunnel

You are the lead developer for an Appian project, in a backlog refinement meeting You are presented with the following user story.

As a restaurant customer. I need to be able to place my food order online to avoid waiting in line for take out.'

Which two functional acceptance criteria would you consider 'good'?

A.

The user will click Save, and the order information will be saved in the ORDER table and have audit history

B.

The user will receive an email notification when their order is completed.

C.

The system mutt handle up to 500 unique orders per day

D.

The user cannot submit the form without filling out all required fields.

You are taking your package from the source environment and importing it into the target environment.

Review the errors encountered during inspection:

Whatis the first action you should take to Investigate the issue?

A.

Check whether the object(UUIDending in 18028821) is included in this package

B.

Check whether the object(UUD ending in 7t00000i4e7a)is included in this package

C.

Check whether the object (UUID ending in 25606) is included in this package

D.

Check whether the object (UUID ending in 18028931) is included in this package