Which of the following is the best tool to use to identify the specific tasks needed to complete a project?

A.

PERT

B.

Activity network diagram

C.

Work breakdown structure

D.

Critical path method

Which of the following actions taken by a change agent will most likely increase resistance to change rather than decrease it?

A.

Encouraging employees to participate in planning and implementing the change

B.

Identifying the stakeholders who will be most affected by the change

C.

Asking employees for input and feedback

D.

Confirming that management is requiring the change

A long-term quality engineer is looking at two equivalent job grade positions to make a lateral move. While the projected salaries for the two positions are the same, the level of responsibility and potential range of influence for one position is significantly greater than the other. Using the Kano Model above, " Salary " is a

A.

exciter

B.

satisfier

C.

dissatisfier

D.

inverse satisfier

Which of the following activities is a main objective for quality function deployment?

A.

Measuring customer satisfaction

B.

Determining the resources necessary for the quality function

C.

Improving customer-supplier relations

D.

Identifying critical quality characteristics at the design stage

A customer submitted a comment card for a hotel chain detailing frustration with the condition of the fitness equipment. Within .1 week, this customer received a letter from the hotel manager apologizing for the inconvenience and a hotel voucher for one night ' s free stay. Upon returning for the free night ' s stay, the customer found the fitness equipment was in the same condition as the first stay, based on this information, the hotel ' s feedback program could best be described as having which of the following characteristics?

A.

Root cause analysis and problem resolution processes

B.

Top management support

C.

A fast response

D.

Properly trained and empowered employees

An internal audit is completed in a company with an ISO-9000 compliant quality system. The audit report shows a major nonconformance in the document control system, in that obsolete procedures are not being withdrawn from use. On receipt of the formal audit report, the management representative should do which of the following?

A.

Retrain all document control personnel in their responsibilities

B.

Advise senior management that corrective action is not required, since none of the obsolete procedures applies to the current contract

C.

Ask the document control manager to form a corrective action team to investigate and resolve the nonconformance

D.

Ask the document control clerk why the established procedure was not followed

Which of the following is an example of an operating expense?

A.

Inventory

B.

Raw materials

C.

Purchased pans

D.

Labor

A new quality manager just found QUI that the company has been awarded three new contracts for the coming year and the quality department had not been informed of these contracts until now. If there is no policy or procedure in the company manual governing advanced quality planning, the manager should do which of the following?

A.

Hire more inspectors and allocate more equipment to cover the new jobs

B.

Attempt to improve communications regarding pending contracts and negotiations

C.

Write a procedure specifying quality department review of new contracts and add it to the company manual

D.

Meet with the other department heads to flowchart an advanced quality planning process

What is the primary benefit of a team developing a vision statement for a new project?

A.

It ensures all team members are aware of their individual responsibilities.

B.

It fosters consensus on shared goals and objectives.

C.

It provides a mechanism for evaluating team performance.

D.

It outlines resource allocation.

A manufacturing company needs to prioritize improvement initiatives based on their impact and feasibility. Which of the following tools should the team use to evaluate and rank these initiatives?

A.

Affinity diagram

B.

Prioritization matrix

C.

Activity network diagram

D.

Tree diagram

Not automating ineffective processes and choosing the lowest technology that gets the job done are examples of understanding the

A.

Fit between the organization and the technology

B.

Fit between Six Sigma and Lean

C.

Relationship between IT and engineering

D.

Relationship between IT and quality

A customer satisfaction questionnaire should have which of the following characteristics?

A.

It should be developed by customer service representatives.

B.

It should solicit information about potential new product offerings.

C.

Its questions should be concise.

D.

Its questions should be limited to product- or service-related issues.

A company ' s new strategic plan targets development of a new service. The quality manager assembles a team from sales and marketing, engineering. Held customer support, finance, and human resources, with the objective of developing a series of matrices that will translate customer requirements into appropriate technical requirements or specifications. The process the quality manager is using to facilitate this outcome is best known as

A.

hoshin planning

B.

design of experiments

C.

quality function deployment

D.

business process reengineering

Which of the following actions by a customer will support long-term relations with a supplier?

A.

Focusing on developing clear purchase orders and contract provisions

B.

Training purchasing staff to facilitate communications between suppliers and end-users

C.

Creating opportunities for the supplier ' s quality engineers to meet with the purchasing staff

D.

Scheduling regular meetings with the supplier to discuss plans and problem-solving options

If an activity time within a critical path is increased, which of the following is most likely to occur?

A.

The project will be delayed.

B.

Additional resources will have to be made available.

C.

Costs will increase.

D.

All activities in the project will be affected.