Which 2 actions should the Project Manager take to implement the new Must
Have requirement?
Time is running short and the Must Have requirements for the data entry screen
of the web page, as recorded in the Prioritised Requirements List, are not going
to be completed on time.
What action should the Project Manager take?
Which 2 actions should the Business Visionary take to implement the new
Must Have requirement?
A difference of opinion on the outcome of an earlier project has created a
' them and us ' culture between the Sales Department and the Operations
Department.
What action should the Project Manager take to resolve this?
Resources are limited. The Sales Manager has two marketing assistants who
may be able to give a few hours a week between them to the project.
What action should the Project Manager take?
During the Foundations phase for Project Increment 4, Sukra Aroon held a meeting with Hira, Mira Bachar, andWanida Anong, to ensure alignment and compliance with EPR company policies, local regulations, and international standards. The meeting also clarified how financial and investment decisions would be made for Project Increment 4, ensuring alignment with EPR business priorities, and how this information will be tracked,
controlled and evidenced.
Wanida Anong, who works across multiple sites worldwide, attended the meeting in person but has limited availability throughout the Project Increment.

(On receiving the meeting invitation, Hira responded suggesting that Brinda Vyas should also be invited to the meeting. Based on AgilePM guidance, which of the following does NOT present an appropriate justification for Brinda Vyas ' attendance?)
(During the Foundations phase, Lee Tan raised concerns about the lack of detailed upfront requirements for the Eco-spa, fearing confusion, constant changes, uncertainty and inefficiency.)
Xan Insurance Company is a friendly company with no separate private offices
for individual managers. Staff members prefer to wander around the office
space and have one-to-one chats rather than use email or have lots of
meetings.
What action should the Project Manager take when planning for effective
communication throughout the Web project?
As Sprint 5 comes to an end, the Infrastructure Delivery Team is facing delays due to:
. Heavy rainfall affecting the Wellness Garden.
. Local supplier issues causing material delivery delays.
· Dependency on external contractors for hydrotherapy equipment.
The Operations Delivery Team is unable to finalize details of the hydrotherapy treatments without testing them in the
context of the facilities being constructed. The marketing materials cannot be generated until this work is complete.
In addition to the Developers, the teams include:

(The Wellness Garden (a Should Have) is delayed. Sukra Aroon suggests a workaround, using the River Pool Patio instead, and classifying the Garden as a ' Won ' t Have this time ' .
Is this an appropriate suggestion?)
Which information could be recorded on an ‘empathy map’ for the marketing staff?