This device is a(n):

A.

micrometer.

B.

digital caliper.

C.

vernier caliper.

D.

engineer's scale.

According to IEEE 841, unless otherwise specified, all electrical performance tests shall be conducted in accordance with:

A.

NEMA MG-1.

B.

IEEE Std 112.

C.

IEEE Std 117.

D.

IEEE Std 522.

According to API 541, the combined runout for areas on the shaft that are to be observed by radial vibration probes shall not exceed:

A.

the maximum vibration amplitude specified in the manufacturer's test criteria.

B.

12.7 µm 0.5 mils.

C.

10% of allowed unfiltered peak to peak vibration amplitude or 3.2 µm 0.125 mils, whichever is greater.

D.

25% of allowed unfiltered peak to peak vibration amplitude or 6.4 µm 0.25 mils, whichever is greater.

Which of the following is a typical topic for the pre-inspection meeting prior to the start of fabrication?

A.

Employee annual leave planning

B.

Quality requirements such as ITP, NCRs, and inspection frequency

C.

Future plant expansion strategy

D.

End-user operating philosophy only

According to ANSI/NETA/ATS, when performing a dielectric withstand test on each bus section, the test voltage shall be applied for how long?

A.

One second

B.

One minute

C.

One hour

D.

One day

According to API RP 540, threaded conduit joints for explosionproof connections should be made with at least how many fully engaged threads?

A.

2

B.

3

C.

4

D.

5

Before starting surveillance, the source inspector should confirm that the supplier/vendor has:

A.

only the latest code editions, regardless of contract requirements

B.

the most current project documents specified in the engineering design

C.

only verbal instructions from procurement

D.

internal procedures but not drawings

Which source inspection effort level is MOST appropriate for the highest-risk equipment?

A.

No source inspection

B.

Final source inspection only

C.

Intermediate source inspection

D.

Resident source inspection

During the course of manufacturing the supplier/vendor may propose design changes that could impact cost, schedule and/or quality. In such cases, the source inspector should:

A.

prepare a summary of the changes made for inclusion in their report and subsequent action by the purchaser.

B.

request that the supplier/vendor develop a cost/benefit analysis for review and approval by the inspector.

C.

prepare a cost/benefit analysis in order to justify their acceptance or rejection of the proposed changes.

D.

request that the supplier/vendor propose such changes in writing for review by the purchaser.

Why should the dates for source inspection scheduled work process events such as the pre-inspection meeting, key inspection events and anticipated shipping date be identified in advance?

A.

To allow coordination with other project members involved in the activity

B.

To ensure that all dates will meet the project schedule and quality requirements

C.

To provide a sound basis for inspection and test planning for each shop

D.

To be able to assign inspectors to the shops in order not to conflict with other projects